Project Oorani Status Report

Here is the latest action plan from Dhan for the Oorani construction at Bhorajguda:

In Bhorajguda, a village level meeting was conducted on 17th Nov, 2008. In this meeting, the community discussed the following

  • The entire village is very busy with cotton harvesting; This will take another 15 – 20 days.
  • The villagers are committed to contributing 25% of the total estimated cost.
  • They planned to start the construction work on 21st November, 2008
  • They planned to complete the Oorani construction by end of December, 2008
Anand Charity has already sent the first installment of funds to Dhan Foundation. A progress report will be sought from Dhan Foundation around December 10th. After review of this report, the second installment of funds will be sent. Help us fund more projects like this one by making a contribution here.